March 2004 – Engineering, procurement, installation and commissioning of stand-alone PV power plant for a relay telecommunication station at AL SHAHAMA in the Emirate of Abu Dhabi, UAE
Customer: UAE GHQ Armed Forces (Signal Corps)
Type of Installation Off-grid
Total Nominal Power 960 W / 24H
Total Peak Power 9,300 Wp
Autonomy 5 days
Main Components:
- 60 Multi-crystalline modules 24V – 155 Wp
- 60 solar batteries 10 OPzV 1000
- 3 Sunnyboys 2500
- 1 Sunny Island SI 4800
- 1 Sunny Boy Control Plus (monitoring device for remote sites)